Construction Log
St Pius X High School, Adamstown, NSW
This page will be regularly updated with photographs and descriptions of ongoing work at St Pius X High School to keep the school community informed of construction milestones and the general progress of the works.
We hope that you enjoy seeing the redeveloped ‘Factory Wing’ take shape!

Existing Conditions Plan

Construction Plan
Week commencing 16 October 2011
Week commencing 9 October 2011
Week commencing 2 October 2011
Week commencing 25 September 2011
Week commencing 18 September 2011
Week commencing 28 August 2011
Week commencing 21 August 2011
Week commencing 30 June 2011
Week commencing 9 June 2011
Week commencing 22 May 2011
Addressed issue of water ingress. Continued setting out of theatres.
Week commencing 15 May 2011
Demolition and further setting out.
Week commencing 8 May 2011
Commenced setting out of Theatre 1 and Theatre 2.
Week commencing 1 May 2011
Demolition.
Week commencing 24 April 2011
Demolition.
Week commencing 17 April 2011
Demolition continued.
Week commencing 10 April 2011
Internal demolition commenced, beginning with all timber items, such as partition walls and linings, and some materials were set aside for later reuse in this or other projects.
Week commencing 3 April 2011
Initial site set up, including:
- installing site shed;
- erecting site fences; and
- arranging access;
Demolition plan: items were marked for demolition with reference to the Architect’s
demolition plan prior to any demolition commencing. During this demolition planning, the location of all existing site services, such as water, electricity and gas, were confirmed.